Tools

No tools required.

Parts

No parts required.

Left Y-carriage plate
  • Left Y-carriage plate

  • Right Y-carriage plate

  • V-Wheel Kit (8 Pcs)

  • Eccentric Nut (4 Pcs)

Add Comment

3mm Allen Key
  • 3mm Allen Key

  • No. 8 Spanner

  • No. 10 Spanner

Add Comment

  • Press the bearing into the delrin V-wheel

  • Place the washer into the centre of the V-wheel

  • Press the second bearing into the other side of the V-Wheel

  • Insert the M5x35 screw through the bearings

No sure if I’m doing something wrong but the M5x35 Allen head screws in the box were shorter…something like 20mm.

Corrie Du Preez - Reply

  • Mount 4 V-wheels to the holes circled in RED with the spacers and locknuts in the V-wheel kits

  • Make sure the V-wheels can turn easily

Add Comment

  • Mount 4 V-wheels to the holes circled in YELLOW with the eccentric nuts instead of the aluminium spacers.

  • Make sure the notch on the eccentric nut faces away from the fixed V-wheel

  • Check if the V-wheels can turn easily

Add Comment

  • Slide the 20x40 V-slot profile in between the V-wheels

  • Turn the eccentric nuts with the No.10 spanner to eliminate the play between the V-wheels and the aluminium profile

  • Ensure the V-wheels are still fastened and can turn easily

  • Remove the aluminium profile

Add Comment

  • Left Y-axis Rail Assembly

  • Right Y-axis Rail Assembly

  • Y-Motor Plate (2 Pcs)

  • Standoff, M3x18, Female-Female (8 Pcs)

  • M3x8 Cap Screw (24 Pcs)

  • M3 Washer (16 Pcs)

  • Y-Motor (2 Pcs)

  • GT2 Pullay, 16 teeth (2 Pcs)

Add Comment

  • 1.5mm Allen Key

  • 2.5mm Allen Key

  • Pratley Pratlock (Included in kit)

  • Sharp Nose Pliers

Add Comment

  • Place motors as shown in picture

  • Place Y-motor plates as shown in picture

  • Mount motors to motor plates with M3x8 cap screws (8 Pcs), M3 washers (8 Pcs) and Pratley Pratlock by using the 2.5mm Allen Key

Add Comment

  • Mount the M3x18 standoffs (8 Pcs) with the M3x8 cap screws (8 Pcs), M3 washers (8 Pcs) and Pratley Platlock in the holes as indicated

  • Hold the standoff with the sharp nose pliers while tighting the M3 cap screw with the 2.5mm Allen Key

Add Comment

  • Fix the GT2 pulleys (2 Pcs) to the motor shafts with the thin flanch facing towards the motor

  • Tighten the grub screws with the 1.5mm Allen Key

Add Comment

  • Place the left and right Y-Motor rails as shown

  • Place the Y-Motor assemblies as shown

  • Mount the Y-motor assemblies to the Y-motor rails with the M3x8 cap screws (8 Pcs), M3 washers (8 Pcs) and Pratley Pratlock through the holes indicated

Add Comment

  • Side covers: Small (2 Pcs), Medium (4 Pcs), Large (6 Pcs)

  • 20x40 Aluminium Profiles (2 Pcs)

  • M5x8 Button Head screw: Small (12 Pcs), Medium (24 Pcs), Large (36 Pcs)

  • M5 Slide T-Nut: Small (12 Pcs), Medium (24 Pcs), Large (36 Pcs)

Add Comment

  • 3mm Allen Key

  • Pratley Pratlock

Add Comment

  • Slide the M5 T-Nuts into the side of the 20x40 V-Slot profile

  • The following quantity T-nuts is required for each machine size:

  • Small: 3 T-Nuts per slot

  • Medium: 6 T-Nuts per slot

  • Large: 9 T-Nuts per slot

Add Comment

  • Use the M5x8 button head screws (6 Pcs per side cover) and mount it to the V-Slot Profile while adding Pratley Pratlock to the screws

  • The side covers should not extend further than the V-Slot profile at the ends and should be against each other in the middle

  • Tighten the screws with the 3mm Allen Key when the covers are in place

Add Comment

  • Side cover assembly (2 Pcs)

  • Y-Rail motor assembly (2 Pcs)

  • M5 plate nuts (4 Pcs)

  • M5x6 Grub Screw (4 Pcs)

  • GT2 Timing Belt

Add Comment

  • 2.5mm Allen Key

  • Pratley Pratlock

  • Side Cutter

Add Comment

  • Slide the Y-Rail assembly onto the Side plate assembly as shown

  • Feed the GT2 Belt below the V-wheel, over the pulley and below the V-wheel on the other side

Add Comment

  • Add Pratley Pratlock to the M5x6 grub screw and Insert it into the M5 plate nut

  • Slide the M5 plate nut over the belt into the V-Slot

  • Clamp the end of the belt by screwing down the M5 grub screw with the 2.5mm Allen Key while pulling the end of the belt

Add Comment

  • Repeat Step 4 for the other side of the belt

  • Pull the belt with the one hand, while fastening the grub screw with the other hand. Else, ask someone else to pull the belt while you tighten the Grub screw.

  • Cut the belt off on both sides with a side cutter so that it is flush with the V-Slot profile

  • The off cut of the belt will be used later on

Add Comment

  • Repeat steps 3 to 5 for the other side as well

  • Check if the pulleys on the motor shafts are inline with the GT2 belt

Add Comment

Finish Line

4 other people completed this guide.

Paul Cronje

Member since: 09/03/2017

2,141 Reputation

28 Guides authored

0 Comments